PTP 800 Series User Guide Installing the IF and ground cables
phn-2513_004v000 (Oct 2012)
5-59
To run the IF cable into the building, proceed as follows:
1
Make an entry point into the building and run the main IF cable into the
building.
2
Ground the IF cable to the external ground bar outside the building entry point,
as described in Making an IF cable ground point on page 5-54.
3
Install the bottom LPU inside the building entry point.
4
Ground the bottom LPU to the master ground bar.
5
Cut any surplus length from the bottom end of the main IF cable and fit an N
type connector, as described in Fitting an N type connector to an IF cable on
page 5-38.
6
Connect the main IF cable (from the ODU) to the SURGE port of the bottom LPU.
7
Connect the LPU-CMU IF cable to the EQUIPMENT port of the bottom LPU and
run it to the location of the CMU.